WIYN T&E Planning
NOTE: Most of the pages linked below are ONLY accessible WITHIN THE NOAO NETWORK.
February 14-16, 2011 generic T&E
Plans for February 14:
Daytime:
- UPS battery change ~9am-10:30am
- Incorporate TKCOMET changes (Behzad)
- Spare 8051 testing (Hutchinson, Corson)
- WTTM spare computer testing (Behzad)
- WHIRC scripting software changes "pauses" (Mills, Corson)
- Install WFS camera and computer (Corson)
- Replace wiyn-1 sound card (Behzad)
Nighttime:
- TKCOMET testing (Corson, Doug, OA)
- WHIRC software testing (Mills, Corson)
Plans for February 15:
Daytime:
- Implement Probes GUI overlay (Mills, Doug)
- Implement WHIRC/MOP software changes (Mills, Allen)
- Contingency for WFScam install/testing (Corson)
- Engineering tour 11:30-2pm (Corson)
Nighttime:
- WHIRC software testing (Mills, Allen)
- WHIRC headers check (Schweiker, Mills, Allen)
- WFScam testing/commissioning (Corson, Mills)
Plans for February 16:
Daytime:
- WTTM xy stage testing (Corson)
- Jenny & Di need access to the bench spec. room and dome flats, etc for setup
Nighttime: