WIYN T&E Planning
NOTE: Most of the pages linked below are ONLY accessible WITHIN THE NOAO NETWORK.
February 29 - March 1, 2012 Generic T&E
Plans for February 29 - March 1:
Daytime:
- New UPS install (Corson)
- Servo tuning (Corson)
- Possible wavefront camera install (Corson)
Nighttime:
- Continuation of UPS install - telescope may be locked out (Corson)
- Possible wavefront camera testing (Corson)
Feb 8-12, 2012 Generic T&E
Plans for February 8:
Daytime:
- Install WHIRC, if not done previously (Corson)
- Router upgrade (Abareshi)
- WHIRC MOP update and testing. Capturing of bad file names in images and graying out of "abort" during readout. (Mills)
- WTTM tuning to get the xy stage functional again (Corson)
- WTTM - enable a script to exercise WTTM's xy stage, for OAs to run nightly (Corson)
- Hydra cradle testing (Goble)
- WHIRC testing and checkout (Joyce/Allen)
Nighttime:
- WHIRC testing (Joyce/Allen)
Plans for Feb 9-12:
Daytime:
- CuAr comparison lamp replacement (Willmarth)
- Contingency for anything not completed the 1st day
Nighttime:
- WHIRC testing (Joyce/Allen)
- Note: Full nights Feb 9/10, but only 1st 1/2 Feb 11/12 are for T&E