June 10-13, 2014 T&E
**Note: This is the switchover from IAS to Hydra so if any issues arise from the changeover all other activities must shift appropriately.
Plans for June 10:
Daytime:
- Instrument change from IAS to Hydra (Corson et al)
Nighttime:
Plans for June 11:
Daytime:
- Instrument change cont'd (Corson et al)
Nighttime:
- ODI testing - ADC, Star tracker, guide star prediction, guider testing (Harbeck, Liu)
- Star Tracker testing (Rajagopal)
Plans for June 12:
Daytime:
- Bench reconfig (Willmarth, Liu)
- ODI shutter testing (Harbeck, Liu)
Nighttime:
- 1st 1/2 - ODI testing (Harbeck, Liu)
- 2nd 1/2 - Star tracker testing (Rajagopal)
Plans for June 13:
Daytime:
- Bench reconfig contingency (Willmarth, Liu)
- Potential ODI shutter work (Harbeck)
Nighttime:
- 1st 1/2 - ODI testing contingency (Harbeck, Liu)
- 2nd 1/2 - Star tracker testing contingency (Rajagopal)
- Saturday's observer is on standby in case of available time (Bastien/Stassun)